ACME Solar Orders 3.1 GWh Battery Storage Systems To Faster Project Rollouts

By BasisPoint Insight

July 8, 2025 at 9:31 AM IST

ACME Solar Ltd. on Monday said it has placed battery energy storage orders totalling over 3.1 GWh across multiple states, with commissioning expected over the next 12–18 months. The orders have been placed with global suppliers such as Zhejiang Narada and Trina Energy, the company said in an exchange filing.

The phased deliveries are scheduled over the next four to eight months of the current financial year. ACME Solar noted that the order value falls within its budget, ensuring capex efficiency, while early procurement is expected to help meet execution timelines and speed up revenue generation.

The renewable energy player currently has an operational capacity of 2,980 MW, with another 4,080 MW under development.